The Press and Journal
Work Starts on Dredging of Canal Debris
Report by Erlend Barclay - 18 September 2002
A massive clean-up operation to remove around 4,000 tonnes of material dumped
by floodwater in the Caledonian Canal at Dochgarroch started yesterday. British
Waterways, the company which manages the canal, is to use a powerful excavator
to remove the mud, rocks and rubble deposited in the waterway during the flooding
on September 8. Since then, boats with a beam of more than 25 feet have been unable
to travel through the affected section.
Originally the firm proposed to dredge the material from the canal bed and dump
it in Loch Ness. But it emerged yesterday the plan was dropped following consultation
with the Scottish Environmental Protection Agency (Sepa). "We didn't tell them
what they should or should not do," said a Sepa spokesman. "Our concern was that
what they did didn't pose a significant threat to the environment. So we just
reminded them of the laws created to protect the environment and reminded them
of their duties as regards the law."
The excavator arrived on-site yesterday afternoon to begin gathering up the material
and transferring it into waiting lorries. The mud will be dumped into the Longman
Tip in Inverness. "As a result of the extensive flooding, rock, gravel and cobbles
were washed into the basin at Dochgarroch," said canal manager Alastair Hamilton.
"Emergency dredging was undertaken by British Waterways to re-open the navigation
channel which, following advice from Sepa, will be disposed of into a landfill
site."
But a boat owner who lived near the blocked section and frequently used the waterway
criticised the decision to dump the material on land. He said: "I don't see why
it couldn't be dumped in the loch. It's about 700 feet deep and it's all natural
material. There's no chemicals so it wouldn't do any damage. The fact that they're
going to close part of the road and take it all to the dump is going to cause
a lot of disruption and use up a lot of time and money. I just don't understand
it."
One lane of the main A82 road will be closed during the operation and temporary
traffic lights set up. The work is expected to last between six and ten days.
|