The Engineers
|
|
|
 |
Ex tunnel engineers Norman Ervine and Harold McCaughan
look through photographs of their work from 50 years ago |
|
On 19th December 2001 Your Place & mine received an email from Norman Ervine of Lisburn which said: "I worked on the tunnel as Assistant Engineer to the Resident Engineer 1950-51. I was present when the breakthrough was made. I well remember the celebrations afterwards!"
Having contacted him we learnt of another engineer, Harold McCaughan living near Bangor Co. Down. That one short email therefore opened a new chapter to the tunnel story. Norman Ervine also graciously provided all of the black and white photographs on this site including the all-important "meeting" picture on page 3.
The two engineers met with us in January 2002
and spent a great day discussing many of the details
about the tunnel from their perspective. There
were two groups of assistant engineers on the
job. One group worked directly for the Consultant
Engineers (Binnie, Deacon & Gourley) and the
other for the Water Commissioners. Mr Ervine and
Mr McCaughan were in the latter group. All engineers
worked to a supreme boss known as the "Resident
Engineer", who was a characterful and somewhat
notorious Englishman called Dr Cyril F Colebrook
who didn't much care for being around when dynamite
was being used. Our engineers discuss..
Listen
to Engineers discussing their chief
|
|
Which way is down?
The gradient of the tunnel was vital to ensure that the volume and flow of the water was what the engineers had predicted. It is easy to see how a mistake in these calculations could have had catastrophic results. Put simply, the tunnel intake had to be an exact prescribed height above the exit. In order to make sure that this was the case the contractors had to make a topographical survey of the land, taking precise levels the whole way round from the Silent Valley to Dunnywater, drawing a contour line as they went. Only then could the relative heights of the two tunnel mouths be determined. The man with the level (left) is Contractor's Engineer, Sam McMurray. The man on the right is the "chainman" - Mr. S McKibben. |
|
|
|
|
 |
An Ingersoll-Rand Drifter used
for drilling deep holes in the granite face
into which explosives were packed. |
|
At the sharp end
Blowing up hundreds of tons of granite in a confined space is an exact science. A series of holes was drilled in the workface to a depth of about nine feet. The pattern and number of these holes was important in order to make the granite break out in the size and shape they wanted. The firing order of the charges was also extremely important, working from the centre outwards in very quick succession, only fractions of a second apart. Click here to view an interactive demonstration of the blasting process.
|
|
|
 |
Engineer
Harold MCCaughan |
|
The drill was mounted on a frame rather like scaffold poles (seen here on left) which had to be reset for each and every hole. Later in the tunnel's development a more streamlined arrangement was used with just a single hydraulic leg, known as an "air-leg". In the picture on the left you can see a number of holes that have been bored.
The drill bit was tungsten carbide tipped and
water-cooled. The drill-rig was powered by compressed
air which was pumped from the outside world. Curiously
the compressors were driven by engines from old
Sherman Tanks. Harold takes up the story..
Listen
to Engineer talk about the crude equipment
The lighting in the tunnel was provided by an outside generator. All of the equipment including the lighting rig had to be moved well away from the face for blasting as it would be destroyed otherwise. |
|
|
|
 |
View showing a flooded tunnel.
The metal horseshoe ribs which were
put in place to uphold the ceiling
can clearly be seen. |
|
A serious setback
It wasn't all plain sailing. When the Dunnywater team was well underneath the mountain the workers ran into what is somewhat understated as "bad ground". There is a huge fissure or 'dyke' in the middle of Slieve Binnian and when they ran into it, instead of drilling into solid granite they were faced with a substance which resembled flowing sand and running water - almost like quicksand. The entire fissure appeared to be draining its contents into the tunnel. No-one knew how far up into the mountain this fissure reached. There might well have been millions of gallons of the semi fluid substance sitting under the pressure of its height, waiting to disgorge into the tunnel. Experts on cementation were called in and it took both great ingenuity and very hard work to overcome the problem. |
|
|
|
 |
| Pumping concrete into a void. |
|
The solution
It was decided that a concrete bulkhead should
be made to stop the flow of water and sand into
the tunnel. Once they had succesfully plugged
it, holes were drilled though it and cement and
water were pumped through them into the void beyond
in the hope that when they mixed with the sand,
concrete might be formed on the other side. The
picture on the left shows the holes in the roof
through which the materials were pumped. Repeating
this cycle of plugging and drilling, they eventually
filled the dyke with solid material and were able
to break through to solid granite once more on
the far side of it. This was a very serious setback
which slowed the progress of the tunnelling dramatically.
For the next six months the tunnel only progressed
42 feet in that heading. Harold explains further..
Listen
to Harold - serious setbacks |
|
|
|
 |
Light at the end of the tunnel for a
three year job of mammoth proportions.
|
|
The day the two tunnels met
During the slow progress of driving two tunnels
which would join into one, careful calculations
and measurements were repeated frequently. There
was also the occasional miscalculation to be corrected.
Norman and Harold cast more light on the candle
theory..
Listen
to Engineers - calculations
As the two teams of workers gradually drove towards each other there came a time when everyone was aware that they should be getting very near to a breakthrough. This was an unnerving time for the engineers as it would prove their calculations to be right or wrong. There were even rumours going about that the teams had passed each other somewhere in the bowels of the mountain. They did meet up as planned however, on the 6th December 1950. it took a few days to recover from the celebrations! Norman Ervine remembers..
Listen
to Norman - celebrations
|
The tunnel was officially opened on 28th August 1952 by Lord Brookeborough.
Click here to view the official programme of events
YOUR RESPONSES
Michael Clarke - June '06
Hi this is one of your reletaves, I am Michael clarke,
Elizabeth McMurrays son I am very intrested in my great
uncle please email back.
Raymond McMurray
My sister Frances and I were delighted to visit the
site exhibition at the Silent Valley in January 2003,
where we saw for the first time a moving picture of
our father, Sam McMurray, standing at the entrance to
the new tunnel. He looks so proud and happy! Sam died
in 1965 and I am eager to learn more about the engineering
project and his work on it, to fill in some of the many
gaps in our memory of him. I would be very interested
to hear from anyone who has anecdotes or photographs
of my late father, who was the contractor's engineer
on the project. I have very little information at present.
your place and mine contributor
I'm searching for a picture of C.F.Colebrook and other
details about his life, especially about the date of
his death. Can somebody help me?
|