Guernsey waste export plan approved by States

Les Vardes Quarry Deputy Luxon said Les Vardes Quarry was one of nine quarries considered as possible landfill sites

Related Stories

A move to throw out Guernsey's waste strategy for the third time has failed.

Deputy Laurie Queripel led the motion to reject the export of waste in favour of continuing to landfill the island's rubbish.

Public Services Minister Paul Luxon said such a reversal would cost several million pound to add to the nearly £12m spend on the two previous options.

Deputies threw out the proposals by a vote of 33-4 and approved a search for companies to manage the waste export.

Deputy Luxon said: "By exporting our residual waste it allows us to continue with the core project... which is to minimise.

Previous waste strategies

  • 1994 It became clear the island's landfill sites, where rubbish was put into old quarries, were running out
  • 1998 The States decided Mont Cuet would be the island's last landfill site
  • 2003 Lurgi UK agreed to build a £72m energy-from-waste plant to deal with 70,000 tonnes of waste annually
  • 2005 An independent panel found the plant would be too big and the aborted project cost the States £6.7m
  • 2009 Suez Environment was chosen to build a £94m waste-to-energy plant capable of dealing with 45,000 tonnes of rubbish a year
  • 2010 Those plans were scrapped at a cost of £4.8m
  • February 2012 Plans to increase recycling and export the remaining waste are approved in principle

"Should we reach the lowest possible level of residual waste at some point in the future then it may well be we can look at other alternative options."

The States has agreed to staggered recycling targets with an overall aim of recycling 70% of household rubbish in 2025, but it failed to reach its 50% target for 2013.

The Public Services Department has estimated the cost of the infrastructure needed for the export of waste to be about £29m.

It will now go out to tender for the construction of a transfer station, someone to transport the waste, a materials recovery facility and other items including vehicles for the kerbside collection of recyclables.

It's not yet been agreed where the waste will be exported to or how it will be dealt with.

Currently, non-recycled waste is dumped at Mont Cuet landfill site in the Vale, which is expected to reach capacity in 2022.

The strategy also includes plans to ensure public events use recyclable food and drink containers and work with the commercial sector to prevent and minimise waste generated by businesses.

More on This Story

Related Stories

The BBC is not responsible for the content of external Internet sites

BBC Guernsey

Weather

Guernsey Airport

18 °C 15 °C

Features

BBC © 2014 The BBC is not responsible for the content of external sites. Read more.

This page is best viewed in an up-to-date web browser with style sheets (CSS) enabled. While you will be able to view the content of this page in your current browser, you will not be able to get the full visual experience. Please consider upgrading your browser software or enabling style sheets (CSS) if you are able to do so.