A74(M)/M74 motorway works' second phase set to start

A74(M) The phased works are scheduled to take place over a period of five years in total

Related Stories

The second phase of a £40m upgrade on the main route between the Scotland-England border and the central belt will start next month.

It is part of a five-year project on the A74(M)/M74 between junction 22 Gretna and junction 12 Millbank.

The first phase of the works was completed in November.

Once finished, the project will deliver more than 80 miles of new road surface on the route that carries more than 30,000 vehicles-a-day.

The work will be carried out by Autolink, which has a contract with the Scottish government's transport agency, Transport Scotland, for the road.

The latest phase gets under way on 23 February.

Traffic will be limited to 40mph through the works and motorists have been advised to allow extra time for their journeys or to consider using an alternative route.

More on This Story

Related Stories

The BBC is not responsible for the content of external Internet sites

BBC South Scotland

Weather

Dumfries

Min. Night 8 °C

Features

BBC © 2014 The BBC is not responsible for the content of external sites. Read more.

This page is best viewed in an up-to-date web browser with style sheets (CSS) enabled. While you will be able to view the content of this page in your current browser, you will not be able to get the full visual experience. Please consider upgrading your browser software or enabling style sheets (CSS) if you are able to do so.