Universal credit - an IT fiasco?

 
DWP sign

It's an ambitious plan to transform the benefits system - but it looks as though the technology meant to power universal credit is turning into another great government IT disaster.

This morning the work and pensions secretary Iain Duncan Smith told the BBC that the planned 2017 deadline for the programme would probably slip - although the DWP statement still talks optimistically of the continued "safe and secure roll-out" of the scheme.

One civil servant close to the situation has painted a rather different picture. He tells me that DWP staff at the frontline are doing a heroic job using the IT but they are "struggling so much with the number of times they have to re-key, systems are crashing. They're not joined up, they just can't cope with the messy reality of people's lives".

The IT system that the DWP is using at the moment is the one severely criticised in a National Audit Office report. It has been developed mainly by big outside contractors such as Accenture and IBM at a cost of more than £300m. Some believe much of that money will have to be written off.

Start Quote

As with many other IT disasters, this is about management rather than technology”

End Quote

Now what the DWP calls a new "enhanced system" is being developed, with far more in-house involvement. Insiders say this is a good move - but wonder why the department did not go down this route in the first place. After all, the government had signalled that the days of huge IT projects, where outlandish sums were handed to big contractors, were over.

But as Iain Duncan Smith makes clear in his statement, both systems - the old one run by Accenture et al, and the new enhanced version - will now run in tandem. Some of the old technology, according to my insider, may be of use, but the effect is to postpone the reckoning of just how much money has been wasted: "They're carrying on as if nothing has changed... they're still spending money trying to make the existing system work because that's what the DWP leadership wants."

Iain Duncan Smith Iain Duncan Smith

So, just as with many other IT disasters, this is about management rather than technology. It's been reported that the secretary of state has fallen out with his senior civil servants, with Whitehall's perceived inability to deliver on policy at the heart of their dispute.

The DWP is not alone in finding the bigger the project, the more likely it is to go wrong. Look across the Atlantic to the failures of the Obamacare website - or indeed rather closer to home at the BBC's own Digital Media Initiative, written off at a cost of £98m.

One common lesson seems to be that you can't just throw money at a project or outsource it to major suppliers. You have to have the skills in-house to understand the problems you are trying to solve and how technology may help. And, for Whitehall at least, you need more respect and higher status within the civil service for the experts who do have those skills.

My insider's conclusion: "Never again should we be spending £300m the way they spent it - as if they were buying a motorway bridge. This way of doing it is broken - it just doesn't work."

 
Rory Cellan-Jones Article written by Rory Cellan-Jones Rory Cellan-Jones Technology correspondent

Who has won the social referendum?

Millions on both sides of the Scottish referendum have taken to tweeting and Facebooking their views on the issues - who has come out on top in the social media battle?

Read full article

More on This Story

More from Rory

Comments

This entry is now closed for comments

Jump to comments pagination
 
  • rate this
    +1

    Comment number 65.

    You mean the yes men, who say yes to everything yet fail to get anything right? Like G4s and A4e? Wasting our tax money on the private sector propping them up lol.

    I need 100 billion to fix the climate :-) Anybody falling for it? Yes lol

  • Comment number 64.

    This comment was removed because the moderators found it broke the house rules. Explain.

  • rate this
    +1

    Comment number 63.

    Perhaps we should allocate the work to GCHQ as they seem to have all the best IT resources & funding

  • rate this
    -1

    Comment number 62.

    60
    Most smallish software houses lack the capacity to do this type of work and would have to take extra people onto the payroll for it - probably contractors rather than permanent employees as they'd only require them for the duration. That's what makes it expensive as most contractors would expect far more than permies because they need to finance the times when they aren't working.

  • rate this
    +1

    Comment number 61.

    I've worked in IT in the private and public sectors, as supplier and customer.
    Real life is complex, solutions to real life problems are complex.
    Politicians are simple and idealistic folk and as such their solutions are simple and idealistic.
    Public sector sits between the two, so finds practical solutions hard to come by, but good private sector involvement can neutralise political naivety.

 

Comments 5 of 65

 

Features

  • Peaky Blinders publicity shotBrum do

    Why is the Birmingham accent so difficult to mimic?


  • Oliver CromwellA brief history

    The 900 year story behind the creation of a UK parliament


  • Image of Ankor Wat using lidarJungle Atlantis

    How lasers have revealed an ancient city beneath the forest


  • TheatreBard taste? Watch

    Are trailer videos on social media spoiling theatre?


  • Agents with the US Secret Service, such as this one, are responsible for guarding the presidentHard at work

    White House break-in adds to Secret Service woes


BBC © 2014 The BBC is not responsible for the content of external sites. Read more.

This page is best viewed in an up-to-date web browser with style sheets (CSS) enabled. While you will be able to view the content of this page in your current browser, you will not be able to get the full visual experience. Please consider upgrading your browser software or enabling style sheets (CSS) if you are able to do so.