BBC HomeExplore the BBC

28 December 2009
Accessibility help
Text only
Inside Out

BBC Homepage

Contact Us

Like this page?
Send it to a friend!

 

West

You are in: Inside Out > West > Gas pipeline

Gas pipeline being laid

Controversial gas pipeline being laid.

Gas pipeline

There’s a battle going on in Gloucestershire. It’s pitting a small but vociferous group of locals against one of Britain’s colossal corporations. What’s causing the clash is a high pressure gas pipeline and a new installation that comes with it.

Timeline

  • March 2006 - open public meeting held in Staunton. Sixteen attend. Protestors claim the lack of interest was down to poor public awareness.
  • April 2006 - National Grid's planning application is submitted to the Forest of Dean.  The application was validated in May 2006. 
  • 11 May 2006 - further public presentation by National Grid who said that no gas or toxins would be emitted from the chimneys.
  • 25 May 2006 - another National Grid presentation, this time telling the public that there would be 12 chimney stacks and not three. Continuing public concern over pollutants.
  • October 2006 - Forest of Dean District Council reject planning permission for the National Grid's Pressure Reduction Installation at Corse.
  • November 2006 - National Grid appeal against the decision.
  • April - May 2007 - Public inquiry takes place.
  • 18 May 2007 - Public inquiry ends.


National Grid is laying nearly 200 miles of pipeline across England and Wales.

It’s a massive engineering task that will cost £840 million.

Project Manager David Mercer says it’s needed to bring in imported gas as our own supplies dwindle.

He says: "By 2010 the UK will need to import some 50% of its gas requirements and that rises to 80% by 2015."

Gas controversy

Liquid Natural Gas will be imported from places like the Middle East via the Welsh port of Milford Haven.

It will then be converted into natural gas and piped at very high pressure along the new pipeline.

Gas pipeline being laid

Whipping up a storm of protest.

The pipeline starts at Milford Haven, skirts the edge of the Brecon Beacons National Park and finishes at Tirley in Gloucestershire, where it will connect to the existing gas network.

But the project has been dogged by protests from the beginning.

In Wales, along the route of the pipeline, people came out in force to object.

Some even chained themselves to the trees.

The protestors managed to hold up work on some stretches of the pipeline until they were evicted.

Nearly two years after work began, the pipe has finally reached Tirley in Gloucestershire, but it’s bringing with it new controversy.

Pipeline

Essential or environmentally damaging?

Fighting National Grid

There are no protestors up the trees in Gloucestershire but the locals are equally determined to fight National Grid on the latest development - not the pipe itself,  but what’s planned at the end of it – a six acre gas plant on a green field site near the villages of Tirley and Corse. 

The new pipe will need to be connected to existing smaller pipes which operate at a lower pressure.

To connect the two, National Grid want to build a Pressure Reduction Installation or PRI.

As well as objecting to the location chosen for the installation, the protest group - Campaign against the PRI - is concerned the plant could become a target for terrorists.

The plant will handle 20 per cent of the country’s gas supplies and they feel it could be vulnerable to attack.  

Protestors

Locals are fighting the National Grid.

Terrorist target?

Local resident and chairman of the campaign group Peter McMurtie says: "Nobody can give a guarantee that this will never be a target for terrorist activity.

"We can't say it will be, National Grid can't say it won't be. Nobody knows. It's unmanned, so you could lob a bomb over the fence and get away in your car."

The campaigners point to a trial at the Old Bailey earlier in 2007.

One of the five men convicted for the fertiliser bomb plots had worked for a contractor to the gas company Transco.

He had stolen CD Roms showing details of the high pressure gas network.

MI5 recorded two of the other men discussing a possible attack on the utilities.

In response to criticism, the National Grid Project Manager David Mercer says: "We work very closely with the government and the government's security services to make sure that our key installations are properly protected.

"Now you'll appreciate I can't really add to that but we have a very good system that we operate with the government's security services on this matter."    

Following over 1,600 letters of objection to the Forest of Dean District Council, plans for the PRI were turned down.

National Grid has appealed and now everybody is waiting for the result of a public inquiry due any day.

Also featured

Phil Vickery discovers it's not just the French who eat snails.

Plus... the man giving it all up to chase a boyhood dream to become an American Wrestling ring announcer.

last updated: 24/10/07

You are in: Inside Out > West > Gas pipeline

Watch Inside Out again via iPlayer
Natures top 40


About the BBC | Help | Terms of Use | Privacy & Cookies Policy